New Facility Construction Gallery 2011 (click on image to reveal larger versions)
Our building prior to the construction was just a bare warehouse with a tall ceiling, cement floor and walls. In this picture you can see we have just had windows installed on the outer wall.
The next step was constructing the framing for the walls, so we could create a data recovery lab, offices for our data recovery specialists and other key components for our data recovery company.
These red blocks are the 18" reinforced concrete walls for the Class 2 Vault. They had just been delivered and are ready for the vault construction. The vault will also be located in our specialized data recovery lab.
Here is an early shot of our Class 2 Vault. The walls have been constructed and welded into place. The 2 ton vault door with double lock system is also fully functional.
This is the main hallway for The Data Rescue Center. It has a very tall, coved-barrel wood ceiling. Behind the glass walls on the right are offices for Technical Support, Engineering, QA Lab, Data Migration Lab and the Main Hard Drive Recovery Lab.
The outdoor signage is being installed.
Our data recovery company is starting to come together now with the addition to our new lobby sign.
Our signage has been added to the front doors and we are ready for customers needing hard drive data recovery services.